FOUNDATION
R.C.C columns, isolated footings up to roof level over 5.5” thick 40 mm BGM in C.C 1:4:8 mix and 3” thick m-sand bed (4ft Height from Ground Level).
FLOORING
Joint free tiles (24" x 24") will be laid with 4" ht skirting.
Toilet floors will be finished with ceramic tiles.
Toilet walls will be finished with wall tiles upto 7' height.
KITCHEN
Kitchen counter will be finished with black granite upto 2' ceramic tiles on the walls along the granite platform.
Stainless steel sink of size 2'6"x1'-6" – no drain board.
DOORS
Main door with Teak wood frame of size 5"x3" withquality wood panel shutters will be provided. Two brass towerbolts, Four brass hinges and quality handle will be provided.
Internal Door in quality frames of size 4"x2.5 " will be used for all internal Doors. UPVC Windows with glass M.S safety grills as per design. Bedroom doors Provided with lock.
Flush doors will be provided for bedrooms and toilets.
UPVC Sliding door will be provided for balcony.
Other floor toilets and balcony – flush door.
PLUMBING
3/4" pipes will be used for water lines to kitchen and toilets, 4" dia rain water pipes will be used to drain water from the open terrace from any two points.
Toilets will have geyser provision with inlet and outlet angle cocks.
A separate water line from the sump will be connected to the overhead water tank. (mono block motor will be provided).
SANITARY FITTINGS
All quality sanitary fixtures.
CP fittings – Parryware / Jaguar fittings / equivalent.
ELECTRICAL
P.V.C pipes will be used for concealed lines heavy duty 2mm pipes for roofs, medium 1.5mm pipes for walls. Orbit wires will be used. Anchor Roma Switches will be provided. M.C.B Type distribution board (Standard) will be provided.
CUPBOARDS AND LOFTS
Open cupboards & loft will be provided in Kitchen & bedroom along any one wall with Kadappa slab.
STAIRCASE
Hand rail will be 3' –0" height with safety grills. Staircase flooring will be finished with cement flooring. Brick work steps will be provided.